Home » » Project Scheduling

Project Scheduling

  Welcome to this video on finding the critical

path on a project network.


I’ll be working with this activity schedule

for a project.


I’ll be constructing a project network,

doing forward and backward passes, determining


the project completion time, calculating slack

values, and finally, stating the critical


path.


I will be using this node convention here

as you will find in Quantitative Methods for


Business by Anderson, Sweeny and Williams.


A here is the activity being described, and

t represents the expected activity duration


or time.


ES is the earliest time the activity can start;

EF is the earliest finish time; LS is the


latest start time, and LF is the latest finish

time without extending the minimum completion


time of the project.


I usually like to start with a sketch to make

it easier when drawing the full network.


Activities A and B have no predecessors so

they can begin at start.


Activity C needs A to be completed before

it can start.


D needs both A and B completed.


E needs D, F needs C and E, and G depends

on E. Since F and G have no successors, they


go to Finish.


So here is the network with the activity nodes,

displaying the letters and times.


So let’s do the forward pass.


A has no predecessor so its earliest start

time will be 0 or right away.


Since it has 7 weeks to be completed, its

earliest finish time will be 0 + 7 which gives


7.


B also has an earliest start time of 0, and

with and activity time of 9, it will have


an earliest finish time of 9.


Now C needs A to be completed before it can

start.


Since the Earliest Finish time for A is 7,

then the Earliest Time C can start is 7.


And with an activity time of 12 weeks, C will

have an Earliest Finish time of 12 + 7 which


gives 19.


D on the other hand needs A and B to finish

before it can start.


Since the Earliest Finish time for A and B

are 7 and 9 respectively, and D needs both


of them to finish in order to start, then

the Earliest Time D can start is 9.


In order words, the highest of the Earliest

Finish Times preceding an activity will be


the activity’s Earliest Start Time.


So D finishes at 8 + 9 which gives 17.


E here has only one predecessor D, and so

can start at 17 and finish earliest


at 26.


F has predecessors, C and E. Since the higher

Earliest finish time is 26, F can start earliest


at 26 and finish at 32.


G also can start earliest at 26 since it has

only one predecessor, E. And G can finish


earliest at 26 + 5 which gives 31.


Note here that although G is the last letter,

it does not have the highest Earliest Finish


Time because F has 32.


So we say that the project’s completion

time is 32 weeks.


In essence, the project’s completion time

is the highest of the Earliest Finish Times


at the Finish node.


Now let’s do the backward pass.


Since the project completion time is 32 weeks,

the latest finish times for the activities


at the finish node, F and G, has to be 32.


That is, F and G cannot be completed in longer

than 32 weeks.


Next we obtain the latest start times by subtracting

the activity times from the latest finish


times.


For G, the latest start time will be 32 minus

5 to give 27.


For F, the Latest Start will be 32 minus 6

and that gives 26.


Now E has 2 successors, F and G.


Their latest start times are 26 and 27 respectively.


As a result, the latest time E has to finish

has to be 26 in order for F to start.


In essence, when doing backward pass, the

latest finish time of an activity must be


the minimum of the latest start times of its

successors.


Thus the Latest start time for E will be 26

minus 9 which gives 17.


Now D has only one successor, E. So the latest

finish time for D will be the latest start


time for E, 17.


And the LS will be 17 minus 8 which gives

9 for D.


Activity C also has one successor, F. Therefore,

latest finish will be 26 for C, and latest


start will be 14.


A has two successors, C and D. The minimum

of their latest starts is 9.


So the latest finish for A will be 9 and its

latest start will be 2.


Activity B has one successor, D, with latest

start of 9.


So the latest finish for B will be 9, and

its latest start will be 0.


The backward pass is now complete.


Now slack for an activity is defined as how

long the activity can be delayed without extending


or increasing the project completion time.


And it is calculated as LS – ES or LF – EF.


So the slack for A will be 2 minus 0 or 9

minus 7.


Which will be 2.


The slack for B will then be 0, for C it will

be 7, for D 0, for E 0, for F 0, and for G


1.


Note, for example, that activity C can begin

anytime between week 7 and 14 and it can finish


anytime between week 19 and 26.


Thus C can be delayed for up to 7 weeks and

the project will still be completed in week


32.


Activities, B, D, E, and F on the other hand

cannot be delayed at all without extending


the project’s completion time.


So, for example if D is delayed by 2 weeks,

then the project completion time will be extended


by 2 weeks as well, from 32 to 34.


The activities with 0 slack are called critical

activities.


And they form the critical path which is the

longest path in the network.


So the critical path here is B-D-E-F.


And that’s it for this video.


Thanks for watching.


Thanks for reading & sharing BELAJAR DIKACANGIN

Newest
You are reading the newest post

0 comments:

Post a Comment

iklan

donation

Donation
Donation For Aray Nctrl

Contact Form

Name

Email *

Message *